High Pressure Steel Gas Main Projects
130,000 Feet Installed
A.M. Ortega has successfully installed over 130,000 feet of high pressure gas main throughout California, Nevada and Arizona. The following is a list of the projects we have recently completed:
- Taft St. & Euclid, Garden Grove, CA
- Harbor Blvd. & Warner Ave., Santa Ana, CA
5,500 LF of 10" HP Steel
- McAllister Pkwy. & Orange Haven Ln., Riverside, CA
- Cartmill Ave. & Prosperity Ave., Tulare, CA
- Rio Bravo & Elks Hill, Shafter, CA
- Victor Valley Transit Authority Project, Victorville, CA
- FR-34 Phase II, Surprise, AZ
- Van Buren Ave. & 16th St., Phoenix, AZ
1,500 LF of 8" HP Steel
- Paradise Hills Rd. & Old Hwy. 2, Henderson, NV
7,000 LF of 10" HP Steel
- Hwy. 111, La Quinta, CA
- Calimesa Blvd. & Ave. K, Calimesa, CA
- Red Hill Ave., Irvine, CA
- Imperial Hwy. & Woodruff Ave., Downey, CA
- Seal Beach Blvd. & I-405, Seal Beach, CA (So Cal Gas)
- Seal Beach Blvd. & I-405, Seal Beach, CA (Long Beach Gas & Oil)
- Monterey Ave. & Gerald Ford Ave., Rancho Mirage, CA
- MTA Bus Depot Main Alteration, El Monte, CA
- Morro Bay Replacement Project, Atascadero, CA
- Red Hill Ave. & Dyer Rd., Santa Ana, CA
10,00 LF of 12" HP Steel
2,700 LF of 8" HP Steel
4,500 LF of 6" HP Steel
40,000 LF of 8" HP Steel
11,000 LF of 8" HP Steel
6,700 LF of 6" HP Steel
500 LF of 6" HP Steel
10,000 LF of 10" HP Steel
1,200' of 8" HP Steel
800 LF of 6" HP Steel
650 LF of 12" HP Steel
720 LF of 12" HP Steel
8,300 LF of 6" HP Steel
1,450 LF of 20" HP Steel
1,487 LF of 10" HP Steel / 84' of 8" HP Steel
1,100 LF of 8" HP Steel